a palisade high security fence in Cabramurra – Snowy Hydro.
summary of services
Our services for this new palisade high security fence in Cabramurra included managing all aspects of the design, permit and construction stages.
design stages
– concept stage –
The concept design stage for this palisade high security fence included the following key considerations:
- Construction during winter
- Sharing the site with another commercial builder
- Sharing the site with Snowy Hydro appointed contractors
- Living away from home considerations for all team members and contractors
- Ground conditions and heavy rainfall
Our ‘order of cost’ included an estimate of costs, the project scope, general specification, health and safety requirements, assumptions and further investigative work required during the ‘develop’ stage.
– develop stage –
We provided recommendations for cost-effective consultants including a draftsman, structural engineer, geotechnical engineer and a building surveyor.
We managed the design team and performed site inspections to confirm the location and depth of in-ground services including power, water, gas, Telstra, NBN, sewer and stormwater.
permit stages
The design of this palisade high security fence triggered several permit requirements including authority report and consent.
We managed the building permit application process on behalf of our clients and provided them with copies of all stamped documentation, permits, insurances and certificates.
construction stages
The project comprised the construction of a new palisade high security fence for the Upper Tumut electrical sub-station as part of expansion works for the Snowy Hydro Scheme. The project scope included:
- 164 lineal metres of palisade high security fencing
- 65 posts – 195 rails – 1,088 palisades – 3,264 bolts
- 1 pair of palisade vehicle swing gates, each 5.5m wide